The standard

CAP·CORE

The 47 standards, listed.

The Capital Project Management System is a document family, not a binder. Each standard below has one purpose, one owner, one place in the lifecycle, and a set of requirements classed as interlock, core, or stretch. Every project the platform deploys carries the family as its document library, with each standard one click away on the step that needs it. The titles and purpose lines here are the register’s own.

Built clean-room on public frameworks (AACE recommended practices, CII front-end planning practice cited, PMI, DCMA and GAO schedule practice, and the applicable API, ASME, IEC, and ISO standards), reviewed by an external panel, and tailored to a site under the Standard or Adoption engagement. The documents themselves are licensed, not downloaded.

This page is the structure: every document, what it is for, who owns it, and where it applies. The documents themselves are read in a walkthrough under NDA, because they are the product rather than the marketing. Book the walkthrough.

GV

Governance & Portfolio

11 documents

Who decides, at which gate, on what evidence, and how the portfolio is planned, funded, measured, and challenged.

GV-00

Tailoring and Conformance Standard

The tailoring layer: Assessment and Deployed modes, the Interlock / Core / Stretch requirement classes, the conformance scale, the tailoring register and the recorded PM variance route.

Owner · Capital projects / engineering function leadEvergreen; reviewed annually and at each client deployment
GV-01

Capital Project Management Standard

The governing rules for how every capital project is classified, gated, funded, assured and closed; the top of the pyramid.

Owner · Capital projects / engineering function leadEvergreen; reviewed annually and after each closeout
GV-02

Capital Portfolio and Long-Range Plan

The rolling multi-year portfolio: every project by stage, class, funding source and year-phased cash flow, integrated with the turnaround long-range plan.

Owner · Capital projects lead with site leadershipStanding; firm 24 months refreshed monthly, rebuilt each budget cycle
GV-03

Project Charter and Business Case

The foundation document for one project: problem, objectives, alternatives screened, funding basis, sponsor and success criteria, and the benefits realization plan Part B measures against.

Owner · Project manager (drafts); project sponsor (owns)Drafted at activity 1.01; approved at G1; re-endorsed at every gate the tier deploys; answered at Part B
GV-04

Gate Governance and Gatekeeper Charter

Who decides at each gate, with what quorum, inputs and recorded outcome; the charters for the portfolio governance body and the project steering committee; the management decision separated from the assurance input.

Owner · Capital projects leadEvergreen; body charters signed and reconfirmed at each phase start; applied at every deployed gate
GV-05

Project Organization and RACI

Roles by tier, the single Responsible and Accountable per activity, and the escalation chain; references the work-process workbook roles sheet.

Owner · Capital projects leadEvergreen; instance per project at G1, field organization chart before G4
GV-06

Project Work Process and Tiering Standard

Governs the tiered work process (Major / Standard / Small / RIK), the complexity calculator, T0 and gate calendaring, and weekly statusing.

Owner · Capital projects leadEvergreen; instance deployed per project
GV-07

KPI and Metrics Dictionary

Definitions and formulas for every portfolio and project metric, with the data source, cadence, owner and known distortions of each, so numbers mean the same thing across projects and years.

Owner · Project controls leadEvergreen; audited annually at the system review
GV-08

Benchmarking and Estimate Validation

How estimates and schedules are validated against history and external benchmarks at each gate.

Owner · Project controls lead (project); custodian of GV-08 (portfolio record and annual review)At G2 and G3 per project (Small at G2 with a G3 refresh; RIK one comparison at the combined gate); annual portfolio benchmarking review by M-8 of the planning cycle
GV-09

Risk Management Standard

Project risk and opportunity register practice, the risk matrix and acceptance authorities, contingency basis by estimate class, hazard-study action tracking, and portfolio-level risk ranking before and after each project.

Owner · Project managerRisk screening at Stage 0 and activity 1.07; register opened at G1; contingency basis at 3.08 (3.05 Small, 3.12 RIK); full refresh before every gate and every assurance review; closed and handed back at G6
GV-10

Funding and Grant Compliance Standard

Funding source classification, authorization ladder, and the conditions register and reporting for grant-funded projects.

Owner · Project controls lead with financeEvergreen; applied at G1, G2, G3, at each supplementary request, and at closeout
FE

Front-End Definition

8 documents

The definition work that earns each gate: alternatives, basis of design, the scope package, the estimate and its basis, contracting, safety in design, permits, and the replacement-in-kind screen.

FE-01

Alternatives and Concept Selection

How credible alternatives, including do-nothing and repair versus replace, are generated, screened and documented before concept lock.

Owner · Project engineerFEL-1 (frame and option study report at activity 1.02, read at G1); concept selected and decision record signed at activity 2.01 (concept lock); read at G2
FE-02

Basis of Design

The design basis document: capacity, service conditions, codes, constraints, and the assumptions every discipline designs to.

Owner · Process engineerRevision A optional in FEL-1; issued and signed at activity 2.01 before G2; approved and frozen at G3; as-built revision at activity 7.01
FE-03

Scope Definition Package Standard

The definition-completeness element set by tier: what a scope package must contain at G2 and G3, scored for the readiness review. Public-framework anchored (CII front-end planning practice cited, not embedded).

Owner · Project engineerG2 draft; G3 complete
FE-04

Estimate Classification and Basis of Estimate

The AACE-class estimate ladder by gate and tier, the definition maturity each class requires, the required Basis of Estimate content, the estimate structure, and risk-based contingency determination.

Owner · Project controls leadClass 5 at G1 (1.04); Class 4 at G2, Class 3 for Small (2.06); Class 3 at G3, Class 2 for Major with bids (3.05); Class 1 check estimate post-G3 for Major
FE-05

Execution Strategy and Contracting Plan

Delivery model, contracting strategy, packaging, the scope-of-work and contract requisition content standards, and the bid cycle, set before sanction.

Owner · Procurement lead with project managerSet at activity 2.05 in FEL-2 and endorsed at G2; updated with bid results at 3.07 and committed at G3; awards executed at 4.03
FE-06

Process Safety in Design

The hazard study ladder from concept to post-startup: method, timing and record standard for each rung, the construction and demolition hazard study, action closure to evidence, and the process safety information handed to operations.

Owner · HSE leadStudy 1 at 1.07; HAZID at 2.02; PHA complete with actions closed before G3 (3.02; 2.02 at Small; 3.03 at RIK); construction and demolition hazard study before mobilization and G4; PSSR at 6.02 (SU-02); post-startup review 3 to 6 months after startup
FE-07

Permitting and Regulatory Plan

Permits, approvals and regulatory notifications with lead times and owners, planned early enough not to gate construction.

Owner · HSE leadFEL-2, activity 2.08 (Major -372/-324, Standard -264/-228, Small -130/-112); register live from G1 to handover acceptance (6.05) and G6
FE-08

Replacement-in-Kind and MOC Screening Standard

The like-for-like test (form, fit, function, materials), the MOC screening between phases, and the single combined gate that keeps RIK projects fit for purpose.

Owner · Project engineer with operationsAt intake, at every gate, and before G3 on all tiers (activity 3.03)
PL

Planning & Readiness

12 documents

Everything that has to be real before the field is mobilized: the execution plan, the schedule, cost control, procurement, packaging, constructability, HSE, quality, the turnaround window, the assurance reviews, communications, and tie-ins.

PL-01

Project Execution Plan

The integrated plan for how the project will be engineered, procured, constructed, commissioned and handed over.

Owner · Project managerDraft at G2; issued and endorsed at G3 (activity 3.04); live to G6
PL-02

Integrated Schedule Standard

Schedule requirements by tier and gate; defers quality scoring to the CAP schedule standards (best practices + quality standard); names the Basis of Schedule as a required instance.

Owner · Project controls leadL1 at G1; L2 at G2; L3 resource-loaded baseline plus Basis of Schedule at G3; L4 before G4; as-built at G6
PL-03

Cost Control and Change Management

Control budget, forecasting, trend and change management, contingency drawdown and reporting after sanction.

Owner · Project controls leadControl budget accepted within 10 calendar days of the G3 late finish; monthly to financial closeout (7.02); field change cycle 5.03 at Major and Standard
PL-04

Procurement and Materials Management

Long-lead identification and the pre-sanction commitment route, purchasing, vendor data, expediting and source inspection, logistics, receipt and positive material identification, site materials control, and surplus and spares handover.

Owner · Procurement leadLong-leads identified at FEL-2 (2.04); pre-sanction commitments approved at G2; purchase orders from 4.02; materials received and verified at 4.05; surplus and spares reconciled at closeout
PL-05

Construction Work Packaging

How construction work packages are built, released and progressed; the construction-project counterpart of the STO·CORE work package standard.

Owner · Construction managerActivity 4.04 (Major -142/-54, Standard -101/-38); packages complete and constraint-free before G4 (4.07); live to MC (5.05); no separate 4.04 at Small, none at RIK
PL-06

Constructability Review Standard

Constructability reviews at concept and pre-construction for Major and Standard tiers.

Owner · Construction managerConcept review at activity 2.09, Major and Standard, before CAP·AR2 and G2; pre-construction review at activity 4.06, Major only, before G4
PL-07

HSE Plan and Permit Strategy

The project HSE plan, simultaneous-operations rules and the work-permit strategy for construction inside a running plant.

Owner · HSE leadIssued for tender with the construction packages (3.07); issued for construction at activity 4.08 before mobilization; tested at G4 (4.07); live to demobilization
PL-08

Quality Plan and ITP Standard

Quality plan, inspection and test plans, hold points and records required for mechanical completion, including the QA criticality evaluation, the design review and technical query procedures, vendor quality and the nonconformance process.

Owner · Project engineerCriticality evaluation with the contracting strategy (2.05); quality plan issued with the PEP (3.04); ITPs approved with the work packages (4.04); readiness check at G4; program executed 5.04; record set complete at MC (5.05)
PL-09

STO Integration and Window Planning

How STO-coupled projects choose and lock a window, pin T0, integrate scope, permits and shared resources, and report through both plans; the project-side twin of STO·CORE SC-04.

Owner · Project manager with STO managerAt window selection (FEL-1/2) and at scope freeze; confirmed at G3 and G4
PL-10

Assurance Review Standard (AR1 to AR4)

The independent assurance reviews ahead of G1, G2, G3 and at closeout: scope, instruments (interviews, polls, readiness score), timing by tier, and how each feeds the gate decision.

Owner · Assurance program owner, independent of project deliveryAR1-AR3 ahead of their gates (1.08, 2.10, 3.11); AR4 after handover (7.04)
PL-11

Communications and Stakeholder Plan

Stakeholder map, reporting cadence and escalation paths for the project.

Owner · Project managerDrafted with the execution strategy (2.05); issued with the G2 gate pack (2.11); reissued with the PEP (3.04); refreshed at every phase transition
PL-12

Interface and Tie-in Management

Registering and managing tie-ins, interfaces with operating units and other projects, and the outage each tie-in needs.

Owner · Project engineerFrom FEL-2 (activity 2.03); frozen at G4 (activity 4.07) or the STO scope freeze if earlier; closed at G6
EX

Execution & Construction

5 documents

Mobilization, progress and earned value, field change, inspection records, and the mechanical completion that ends construction.

EX-01

Site Mobilization and Logistics

Laydown, access, utilities, security and contractor mobilization requirements.

Owner · Construction managerSite logistics plan drafted at Concept Definition, approved before G4 (4.07); mobilization authorizations per contractor; site mobilization complete at activity 5.01
EX-02

Progress Reporting and Earned Value

Progress measurement rules by tier, the earned-value calculation where warranted, and the daily, weekly and monthly report content standards.

Owner · Project controls leadThroughout execution
EX-03

Field Change Management

How field changes are raised, classified, approved and costed without eroding the sanction basis.

Owner · Project managerActivity 5.03, T0 to mechanical completion (Major T0+9 to +162; Standard T0+4 to +81); carried inside activity 5.02 at Small and RIK
EX-04

Construction Quality and Inspection Records

Inspection records, NCRs and the quality dossier that supports mechanical completion.

Owner · Project engineerThroughout construction (activity 5.04); dossier indexes issued with the packages at 4.04; record set transferred at 7.01
EX-05

Mechanical Completion and Punch List

MC definition, punch categories (A/B/C), and the certificate that ends construction.

Owner · Construction managerActivity 5.05, system by system; T+166 to +180 Major, +83 to +90 Standard, +28 to +30 Small, +13 to +14 RIK
SU

Commissioning & Startup

3 documents

Systems completion and turnover, the pre-startup safety review, and commissioning through the performance test.

SU-01

Systems Completion and Turnover

System-based completion, turnover packages and acceptance by operations.

Owner · Commissioning leadSystem breakdown frozen at G4 with the tie-in freeze; turnover from MC (5.05) through handover acceptance (6.05); final acceptance before G6
SU-02

PSSR Standard (Pre-Startup Safety Review)

Pre-startup safety review requirements for project scope, including RIK, before energization or introduction of process fluids.

Owner · HSE leadActivity 6.02: after systems turnover and commissioning, before G5 and any energization or introduction of process fluids
SU-03

Commissioning, Startup and Performance Test

Commissioning plan, startup sequence, performance test criteria and acceptance.

Owner · Commissioning leadCommissioning plan approved before G4 (4.07); workpacks executed at 6.01 to hold point 2; ready-for-feed and performance test at 6.04 after the PSSR (6.02) and G5 (6.03); closes at handover acceptance (6.05)
CL

Closeout & Improvement

4 documents

As-builts, the financial closeout and funding compliance report, the lessons and benchmark record, and the post-investment review.

CL-01

Documentation and As-Built Closeout

As-builts, vendor data, and the engineering records handed to operations and maintenance.

Owner · Project engineerRegister live from G1; process safety information subset as-built before the PSSR (6.02); documentation closeout at 7.01; verified by sample before Part A (7.04a)
CL-02

Financial Closeout and Funding Compliance Report

Final cost report against sanction, and the compliance report against the grant conditions register for funded projects.

Owner · Project controls leadWithin the closeout window
CL-03

Lessons Learned and Benchmark Record

The lessons register held from charter to final action closure, captured against the gates, and the benchmark record (cost, schedule, definition score, outcome) filed to the portfolio history.

Owner · Project managerRegister opened at charter approval (1.01) and held to final action closure; lessons session and benchmark record at 7.03; record locked at Part A (7.04a); filed at G6; Part B outcome field at 7.06
CL-04

Closeout Report and Post-Investment Review

The closeout report and the look-back against the business case, fed by AR4; the record that closes the project and informs the next portfolio cycle.

Owner · Project managerAR4 (7.04) then closeout gate G6 (7.05); Part B post-investment review 6 to 18 months after startup
DP

Delivery Profiles

4 documents

The systems analogs for control-system and business-system projects, where commissioning and cutover carry the weight and civil falls away.

DP-01

Digital and Control Systems Risk in Design

The systems analog of FE-06: information security, data integrity, business continuity and the functional-safety interface, assessed from concept to go-live, for control-system and business-system projects.

Owner · Project engineer, with the site cyber and functional-safety authoritiesAssessment plan with the basis of design (2.02s); detailed assessment closed before G3 (3.02s); verification before the PSSR at C (6.01c)
DP-02

Cutover and Interface Planning

The systems analog of PL-09 and PL-12: the cutover window and freeze, the interface register and integrations, rehearsals and rollback, for control-system and business-system projects.

Owner · Project engineer (interfaces); commissioning lead as cutover leadInterface register from 2.03b; window record at 2.07b and 4.14; interface and cutover packages with rehearsal 1 before G4 (4.04t)
DP-03

Build, Configuration and Test Records

The systems analog of EX-04 and EX-05: release and work packages, environments and migration trials, test execution with one defect register and severity classes, and integration test complete as the freeze, for business-system projects (partly for control systems).

Owner · Construction manager as build and test leadPackages and test plans before G4 (4.04s, 4.09s); test execution through P5 (5.04s); integration test complete and freeze at the end of P5 (5.05s)
DP-04

Go-Live Readiness, Cutover and Hypercare

The systems analog of SU-01 to SU-03: the cutover runbook, user acceptance test and dress rehearsal, the go-live readiness review, the go/no-go authorization, cutover, hypercare and the transition to service, for business-system projects and the go/no-go step of control-system projects.

Owner · Commissioning lead as cutover leadRunbook approved at the start of P6 (6.00s); UAT and rehearsal (6.01s); readiness review before G5 (6.02s); go/no-go (6.03s); cutover and hypercare (6.04s); hypercare exit (6.04t); transition to service at 6.05

Own the standard, not a black box.